§ 49-4. Bracing and shoring.  


Latest version.
  • No person shall within the Village of Hewlett Harbor dig, construct or excavate a cesspool, well, trench, ditch or similar excavation five feet or more in depth or permit any such cesspool, well, trench, ditch or excavation to be dug, constructed or excavated unless the walls or side thereof shall, at all times during the progress of the work and permanently after the completion thereof, be securely braced, shored and supported with boards, timbers, walls or other supports approved by the Building Inspector.